November 27, 2026 — The Middlesex Hospital Alliance (MHA) is preparing to temporarily relocate patients from 1 South and the Intensive Care Unit (ICU) at Strathroy Middlesex General Hospital (SMGH) to a refreshed fourth-floor space on Thursday, December 10, 2026, beginning at 10 a.m.
The move marks an important milestone in the SMGH Patient Room Renewal Project, a significant infrastructure initiative that will allow critical improvements to be completed on 1 South, 2 South and the ICU over approximately two years.
The project includes asbestos abatement, heating, cooling and ventilation upgrades, and other enhancements to support the safety, comfort and longevity of these essential inpatient areas while supporting the hospital’s future redevelopment plans.
“We are pleased to be reaching this important milestone in the SMGH Patient Room Renewal Project,” said Julie McBrien, MHA President & CEO. “We are deeply grateful to the Province of Ontario for its $10 million investment through the Health Infrastructure Renewal Fund (HIRF), which will address critical infrastructure needs, support the renewal of essential hospital spaces, and help ensure our patient care environments remain safe, comfortable and functional for the patients and families we serve. We recognize the significant planning and coordination required to temporarily relocate patients, and are grateful to our staff, physicians, volunteers and everyone involved in preparing for this transition.”
Preparing for temporary patient care
The refreshed fourth floor has been prepared to accommodate patients safely during 1South, 2South, and ICU renovations and provide the clinical functionality required to support their care.
The temporary unit will have a total capacity of 33 beds, including five ICU beds, and will include:
- Temporary ICU beds
- Negative-pressure rooms
- Telemetry capability
- Clinical and support spaces required to provide patient care
Furniture from the Palliative Care suite on 1South will also be relocated to support patients receiving end-of-life care.
Patient amenities have also been considered as part of the planning process, with input from staff and the MHA’s Patient and Family Advisory Council (PFAC). While televisions will not be available in patient rooms on the fourth floor, each bed will have a tablet for patient use, and Wi-Fi will be available for patients who wish to use their own devices.
Once renovations on 1South, 2South and the ICU are complete, which are expected to take 2 years, the temporary fourth-floor unit will close and remain inactive until funding is secured to permanently renovate the space.
Supporting a safe transition
Extensive planning and coordination are underway to support patient relocation on December 10. Additional staff and volunteers will be available to help facilitate the move and support patients and families throughout the transition. More detailed information will be shared with patients and families who are expected to be in the hospital on the day of the move.
Keeping patients, families and the community informed
The MHA recognizes that changes to the hospital environment can raise questions for patients, families, and visitors. Information about the temporary relocation and what to expect will be shared through the MHA website, social media channels, patient information materials, and other communication channels as appropriate.
The MHA appreciates the flexibility, teamwork, and dedication of its staff, physicians, and volunteers as they prepare for this important transition. Together, these efforts will help ensure patients continue to receive safe, quality care close to home while essential improvements are made to SMGH’s inpatient spaces.
For questions or concerns, please contact MHA patient relations at patientrelations@mha.tvh.ca.